Metrics
Updated

PM compliance

PM compliance is the percentage of preventive maintenance tasks completed within their scheduled window over a period.

What PM compliance means in plain language

PM compliance answers a simple question: of the preventive tasks that were due, how many were done on time? It measures execution, not effectiveness. A high figure means the plan is being followed. It does not prove the plan is the right one.

The word that matters is window. Each task needs a due date and an allowed margin, such as a few days either side, and only a task finished inside that margin counts.

Formula

PM compliance = PM tasks completed within window / PM tasks due × 100

PM tasks completed within window
Preventive tasks finished inside their allowed margin around the due date.
PM tasks due
All preventive tasks whose due date fell in the period, whether or not they were done.
ExampleHypothetical numbers

Hypothetical month, one plant

  • 40 preventive tasks were due. 34 were completed inside their window and 6 were late or skipped.

PM compliance = 34 / 40 × 100 = 85%.

Why it matters in maintenance

Compliance measured without a window is meaningless, because a PM done two months late still counts as done. With a window, the number shows whether preventive work is really happening when planned, or being pushed back whenever the plant is busy.

It is also an early indicator. Compliance usually slips before breakdowns rise, so a falling figure is a prompt to look at crew capacity and backlog.

Common measurement mistakes

Three mistakes account for most misleading figures.

  • No window: any late completion counts as compliant.
  • Counting only tasks that were created, not tasks that should have been: a skipped schedule never appears in the total.
  • Averaging across all machines: a plant-wide 90% can hide a critical machine at 40%. Look at the figure per machine.

How Firmicore relates

Firmicore has a PM compliance dashboard with per-machine and per-technician trends, on the Workshop plan and above. It works from the same preventive maintenance schedules and completions your team records, so the figure is not rebuilt by hand each month.

Frequently asked questions

What is a good PM compliance rate?

There is no universal benchmark worth quoting. Set a target for your own plant, track it per machine and watch the trend, paying most attention to critical assets.

Does high PM compliance mean fewer breakdowns?

Not automatically. It shows tasks were done on time. If breakdowns persist, the tasks may not address the real failure modes.

Browse all 34 glossary terms